Dummy Activities (Edexcel IAL Maths)
Dummies
Spec point —
4.1
What is a dummy activity?
-
A dummy activity is an activity that has a weight of zero
- Dummies are not assigned names (letters)
- Dummies are represented by dotted lines
-
Dummies are only used to show precedences in more complicated activity networks
When and where are dummies used in an activity network?
-
Two situations can lead to the need for a dummy activity
-
The first situation is to ensure each activity (arc) has a unique pair of start and end nodes
-
E.g. In the activity network below, activity D has immediate predecessors B and C
- B and C cannot both start at event (node) 1 and end at event (node) 2 (this would not be a unique pair)
- a dummy activity is used so that B has start/end pair (1, 3) and C has start/end pair (1, 2)
-

-
Note that the dummy could also go from event 2 to event 3 with activity D commencing from event 3
-
The second situation that requires a dummy is when there is a split of immediate predecessors
-
E.g. In the activity network below, activity D has immediate predecessors B and C
- Activity E only has B as an immediate predecessor
- A dummy activity is used to show that D depends on both B and C
-

Exam Hint
Exam questions will not always require you to draw the whole activity network
- A diagram of part of the network may be given
Exam questions are often specific about the number of dummies you should use
- If you think you need more, go back to see if you can make improvements
- It is generally expected that an activity network is as concise/efficient as possible with the minimum use of dummies
Worked Example The activities involved in a project are listed in the precedence table below.
Activity Immediately preceding activities Duration (days) A - 5 B - 4 C A 7 D B 3 E A, D 7 F B 6 G C 6 H C 4 I G, H 5 J E, F 4 The project is also represented on the partially completed activity network below.
Using exactly two dummy activities, complete the activity network by adding activities D, E, G, H, I and J.
Answer:
Activity D is dependent on activity B so draw an arc from event/node 2 for D
Looking ahead, activity E is dependent on both A and D, whereas activity C is dependent on just A This is the second situation ('split predecessors') for the use of a dummy activity
Also from looking ahead activity J depends on both E and F - so the arcs for E and F will need to meet
Activities G and H are both dependent on C, and activity I is dependent on both G and H This could lead to G and H having the same start/end node pair This is the first situation ('unique start/end node pair') for the use of a dummy activity
No activities depend on I so its arc can be drawn to the end of the project (sink node)
The activity network can now be completed with activity J and the sink node